Thames Gateway Progress News

We will be frequently updating this page with progress on the Thames Gateway Site.

10th October 2015

Volker Fitzpatrick are happy to confirm that almost 75% of the piling has been completed on site to date:
click on image to enlarge

IMG_1692

21st August 2015

CUML was awarded its Environmental Permit, by the Environment Agency.

17th August 2015

Good news, OFGEM confirmed today that the Thames Gateway Project has been re-approved for Preliminary Accreditation for ROCS (after a change in design required a new application)

1st August 2015

Some arial photographs of the construction progress on site:
click on images to enlarge
photo

Untitled

5th February 2015

We are pleased to announce that construction began on site at the beginning of this month. Starting with enabling works including earthworks and piling.

December 2014

CUML is pleased to announce that it closed on Plot 2 on the Sustainable Industries Park. CUML have a 999 year lease on the site in East London, Dagenham.

May 15th 2014

CUML is happy to announce it achieved planning for the EfW facility on the LSIP. This was a unanimous decision and was granted in record time.

10th March 2014

Latest colour design of the facility.

3d colour plan

 

 

 

 

 

6th January 2014

The full Environmental Statement for the Thames Gateway Facility, submitted to the Barking & Dagenham planning department.

Environmental Statement for proposed energy generation facility at LSIP Plot 2 – December 2013

12th December 2013

Latest conceptual designs for the Thames Gateway facility have been completed and detailed design has commenced.

Screen Shot 2014-01-08 at 16.04.50Screen Shot 2013-12-12 at 14.10.12Screen Shot 2013-12-12 at 14.02.20

 

29th November 2013

Invitation for Chinook Urban Mining’s Public Consultation for the Local Barking & Dagenham community to learn more about the scheme on the Sustainable Industries Park on 10th December 2013.

invitation to public consultation A5